Old Road/Lee's Lane Water, Storm & Sewer Installation
Grand Bank, Newfoundland and Labrador
Federal contribution
$559,891
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 7, 2016
ApprovedSep 13, 2016
201720182019
Built
Approved 2 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Grand Bank
- Construction start
- Jul 7, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start7 months lateforecast Nov 21, 2016
- Construction end9 months lateforecast Mar 31, 2018
Also in Grand Bank