Municipal Dam Analysis and Upgrading - Town of Grand Bank
Grand Bank, Newfoundland and Labrador
Federal contribution
$240,598
Federal share40%
of $601.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
2020202120222023
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Grand Bank
- Construction start
- Jun 5, 2021(actual)
- Construction end
- Mar 22, 2023(actual)
Against the original forecast
- Construction start7 months earlyforecast Jan 6, 2022
- Construction end4 months lateforecast Nov 30, 2022