Municipal Dam Analysis and Upgrading - Town of Grand Bank

Grand Bank, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$240,598
Federal share40%

of $601.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2020202120222023
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Grand Bank
Construction start
Jun 5, 2021(actual)
Construction end
Mar 22, 2023(actual)

Against the original forecast

  • Construction start7 months earlyforecast Jan 6, 2022
  • Construction end4 months lateforecast Nov 30, 2022