Riverside East Watermain Replacement
Grand Bank, Newfoundland and Labrador
Federal contribution
$225,816
Federal share40%
of $564.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Grand Bank
- Construction start
- May 30, 2022(actual)
- Construction end
- Nov 20, 2022(actual)
Against the original forecast
- Construction end3 months earlyforecast Feb 19, 2023