Water and Sewer
Grand Bank, Newfoundland and Labrador
Federal contribution
$264,869
Federal share33%
of $794.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Grand Bank
- Construction start
- Apr 15, 2010(actual)
- Construction end
- Aug 1, 2011(actual)
Against the original forecast
- Construction start6 months lateforecast Oct 15, 2009
- Construction end16 months lateforecast Apr 1, 2010
Also in Grand Bank
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26687 in the federal list. How to read these figures.