Back to projects

Water and Sewer

Grand Bank, Newfoundland and Labrador

completeDrinking WaterCC Top Up
Federal contribution
$264,869
Federal share33%

of $794.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Grand Bank
Construction start
Apr 15, 2010(actual)
Construction end
Aug 1, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 15, 2009
  • Construction end16 months lateforecast Apr 1, 2010