North Vancouver - Library Solar Water Installation

North Vancouver, British Columbia

completeGreen EnergyMRIF
Federal contribution
$102,076
Federal share33%

of $306.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2007
20082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of North Vancouver
Construction start
Jul 10, 2007(actual)
Construction end
Mar 31, 2009(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 22, 2007

Also in North Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17598 in the federal list. How to read these figures.