Water Booster Pumping Station
Massey Drive, Newfoundland and Labrador
Federal contribution
$173,452
Federal share33%
of $520.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.4 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Massey Drive
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Sep 24, 2012(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 1, 2009
- Construction end2.8 years lateforecast Nov 30, 2009
Also in Massey Drive
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18795 in the federal list. How to read these figures.