Back to projects

Road Upgrading-Phase 2

Massey Drive, Newfoundland and Labrador

completeHighways and RoadsCC Top Up
Federal contribution
$158,069
Federal share33%

of $475.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Massey Drive
Construction start
May 12, 2010(actual)
Construction end
Nov 17, 2010(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 14, 2009
  • Construction end2 months earlyforecast Jan 31, 2011

Also in Massey Drive