Road Upgrading-Phase 2
Massey Drive, Newfoundland and Labrador
Federal contribution
$158,069
Federal share33%
of $475.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Massey Drive
- Construction start
- May 12, 2010(actual)
- Construction end
- Nov 17, 2010(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 14, 2009
- Construction end2 months earlyforecast Jan 31, 2011
Also in Massey Drive
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26720 in the federal list. How to read these figures.