Twinning of Sanitary Sewer Main

Massey Drive, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$161,648
Federal share26%

of $627.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Massey Drive
Construction start
Aug 1, 2016(actual)
Construction end
Oct 24, 2016(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2016
  • Construction end12 months earlyforecast Oct 31, 2017

Also in Massey Drive

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46673 in the federal list. How to read these figures.