Lady Diana Crescent Water and Sewer Replacement

Massey Drive, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$249,306
Federal share40%

of $627.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2020
20212022
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Massey Drive
Construction start
Jun 21, 2021(actual)
Construction end
Aug 12, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 24, 2021
  • Construction end6 weeks lateforecast Jun 30, 2022

Also in Massey Drive

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56908 in the federal list. How to read these figures.