Massey Drive Sanitary Sewer Lift Station #1 Overflow Tank
Massey Drive, Newfoundland and Labrador
Federal contribution
$38,180
Federal share40%
of $95.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.3 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Massey Drive
- Construction start
- Jul 22, 2024(actual)
- Construction end
- Sep 26, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast May 3, 2024
- Construction end3 months lateforecast Jun 15, 2024