Schedule

Announced and approvedJul 23, 2021
2022
Built
Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Massey Drive
Construction start
Jun 17, 2022(actual)
Construction end
Jul 4, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 3, 2022
  • Construction end4 weeks lateforecast Jun 7, 2022