Water/Sewer Upgrading and Road Work - Pearson Place

Grand Bank, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$162,446
Federal share33%

of $487.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.6 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Grand Bank
Construction start
Aug 21, 2009(actual)
Construction end
Nov 2, 2011(actual)

Against the original forecast

  • Construction end20 months lateforecast Feb 28, 2010

Also in Grand Bank

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27226 in the federal list. How to read these figures.