Wastewater Treatment Facility Upgrade - Falmouth
Federal contribution
$858,235
Federal share33%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2009
200920102011
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of the District of Hants West
- Construction start
- Mar 18, 2010(actual)
- Construction end
- Mar 17, 2011(actual)
Against the original forecast
- Construction start8 months lateforecast Aug 1, 2009
- Construction end2 weeks earlyforecast Mar 31, 2011
Also in Windsor