Tongue Hill water transmission main upgrade
Federal contribution
$447,778
Federal share47%
of $959.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Windsor
- Construction start
- Jul 28, 2017(actual)
- Construction end
- Feb 27, 2018(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 1, 2017
- Construction end5 weeks earlyforecast Mar 31, 2018
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47203 in the federal list. How to read these figures.