Gerrish street water and sewer systems renewal
Federal contribution
$457,665
Federal share50%
of $915.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Windsor
- Construction start
- May 30, 2017(actual)
- Construction end
- Nov 3, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2017
- Construction end5 months earlyforecast Mar 31, 2018
Also in Windsor