$32,000,000
Federal share50%
of $64.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 17, 2019
today
2019202220252028
BuiltForecast
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Nova Scotia Department of Public Works
- Construction start
- Apr 20, 2020(actual)
- Construction end
- Dec 31, 2029(forecast)
Against the original forecast
- Construction start11 months lateforecast Jun 1, 2019
Also in Windsor