New Wastewater Treatment Facility

Windsor, Nova Scotia

completeWastewaterCC
Federal contribution
$2.9M
$2,903,517
Federal share29%

of $10.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2009
2009201120132015
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Windsor
Construction start
Jan 1, 2011(actual)
Construction end
Jun 10, 2016(actual)

Against the original forecast

  • Construction start3.4 years earlyforecast May 15, 2014
  • Construction end7 weeks earlyforecast Aug 1, 2016

Also in Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28160 in the federal list. How to read these figures.