Highway 101 Twinning: Three Mile Plains to Falmouth
Federal contribution
$34.5M
$34,500,000
Federal share50%
of $69.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2018
2018202020222024
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Mar 5, 2018(actual)
- Construction end
- Sep 30, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jan 1, 2018
- Construction end3.2 years earlyforecast Dec 31, 2027
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46647 in the federal list. How to read these figures.