North Vancouver - Lynnmour Dike Flood Protection

North Vancouver, British Columbia

completeDisaster MitigationCC Top Up
Federal contribution
$142,780
Federal share33%

of $428.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
District of North Vancouver
Construction start
Jul 12, 2010(actual)
Construction end
Aug 26, 2010(actual)

Against the original forecast

  • Construction start10 months lateforecast Sep 23, 2009
  • Construction end7 months earlyforecast Mar 31, 2011

Also in North Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27713 in the federal list. How to read these figures.