Highway 33 - Walker Hill Climbing Lane
Federal contribution
$1.6M
$1,632,660
Federal share50%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Oct 9, 2010(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Oct 31, 2010
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Highway 97 - Highway 33 to Edwards$18.0M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Septic System Elimination and Sewer Connection$4.9M
- Kelowna - Mission Creek Bridge$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29008 in the federal list. How to read these figures.