Gordon Drive Multi-Purpose Pathway
Federal contribution
$350,000
Federal share25%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Kelowna
- Construction start
- Jul 30, 2010(actual)
- Construction end
- Aug 1, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 15, 2010
- Construction end4 weeks earlyforecast Aug 31, 2011
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Highway 97 - Highway 33 to Edwards$18.0M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Septic System Elimination and Sewer Connection$4.9M
- Kelowna - Mission Creek Bridge$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29401 in the federal list. How to read these figures.