Chalmers Line Culvert Replacement

Dutton/Dunwich, Ontario

completeHighways and RoadsISF
Federal contribution
$81,064
Federal share26%

of $315.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 1, 2010(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2011

Also in Dutton/Dunwich

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30401 in the federal list. How to read these figures.