Back to projects

Bouctouche Municipal Building

Bouctouche, New Brunswick

completeRecreationISF
Federal contribution
$5.0M
$5,000,000
Federal share25%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 15, 2009
ApprovedJul 28, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Bouctouche
Construction start
May 3, 2010(actual)
Construction end
Oct 31, 2011(actual)

Also in Bouctouche

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35024 in the federal list. How to read these figures.