Construction of a Drinking Water Treatment Plant and Extension of the Network
Federal contribution
$1.1M
$1,057,572
Federal share48%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Bouctouche
- Construction start
- Jun 5, 2017(actual)
- Construction end
- Apr 20, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2017
- Construction end5 months lateforecast Nov 30, 2019
Also in Bouctouche
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47293 in the federal list. How to read these figures.