Construction of a Drinking Water Treatment Plant and Extension of the Network

Bouctouche, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$1.1M
$1,057,572
Federal share48%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Bouctouche
Construction start
Jun 5, 2017(actual)
Construction end
Apr 20, 2020(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2017
  • Construction end5 months lateforecast Nov 30, 2019