Bouctouche Lagoon Upgrades

Bouctouche, New Brunswick

completeWastewaterCVRIS
Federal contribution
$2.4M
$2,400,000
Federal share75%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Bouctouche
Construction start
May 2, 2022(actual)
Construction end
May 31, 2023(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 16, 2022