Pays de la Sagouine Repositioning
Federal contribution
$21.1M
$21,130,632
Federal share60%
of $35.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 23, 2022
today
202320242025202620272028
BuiltForecast
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Pays de la Sagouine
- Construction start
- Apr 1, 2023(actual)
- Construction end
- Mar 31, 2028(forecast)
Against the original forecast
- Construction start2 months earlyforecast Jun 2, 2023