Back to projects

Improvements to the water and wastewater system

Bouctouche, New Brunswick

completeDrinking WaterSCF
Federal contribution
$1.1M
$1,144,963
Federal share33%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2015
2016201720182019
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Bouctouche
Construction start
Oct 17, 2016(actual)
Construction end
Jul 31, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 4, 2016
  • Construction end8 months lateforecast Dec 1, 2018

Also in Bouctouche

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46076 in the federal list. How to read these figures.