Rehabilitation of Wastewater System
Federal contribution
$1.1M
$1,088,553
Federal share45%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Bouctouche
- Construction start
- Nov 20, 2017(actual)
- Construction end
- Mar 15, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Sep 1, 2017
- Construction end3 months lateforecast Nov 30, 2019
Also in Bouctouche
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48177 in the federal list. How to read these figures.