Port Metro Vancouver North Shore - Access Road
North Vancouver, British Columbia
Federal contribution
$60,000
Federal share50%
of $120.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 23, 2009
ApprovedJan 29, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Vancouver Fraser Port Authority
- Construction start
- Aug 24, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction end5 months lateforecast Oct 31, 2010
Also in North Vancouver