Repaving Route 515
Federal contribution
$920,968
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 14, 2011
2011
Built
Approved 6 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2010