John Hindle Drive Extension (Phase 2)

Kelowna, British Columbia

completeHighways and RoadsMIC
Federal contribution
$3.1M
$3,124,163
Federal share30%

of $10.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedNov 10, 2014
ApprovedMar 31, 2015
2015201620172018
Built

Approved 5 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
May 15, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start19 months lateforecast Oct 15, 2015