Kelowna University of British Columbia Okanagan (UBCO) Exchange
Federal contribution
$1.4M
$1,352,380
Federal share50%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 19, 2016
2017
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- British Columbia Transit
- Construction start
- May 31, 2017(actual)
- Construction end
- Sep 3, 2017(actual)
Against the original forecast
- Construction end3 months earlyforecast Nov 30, 2017
Also in Kelowna
- Kelowna Integrated Water Project - Phase 1 (South East Kelowna Irrigation District/South Okanagan Mission Irrigation District Water Supply Project)$26.4M
- Highway 97 - Highway 33 to Edwards$18.0M
- Kelowna RapidBus Transit$7.0M
- Kelowna - Septic System Elimination and Sewer Connection$4.9M
- Kelowna - Mission Creek Bridge$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46954 in the federal list. How to read these figures.