Tatamagouche sewage collection system replacements ph 3&4
Federal contribution
$230,835
Federal share50%
of $461.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the County of Colchester
- Construction start
- Oct 20, 2017(actual)
- Construction end
- Nov 13, 2018(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2019
Also in Colchester
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47237 in the federal list. How to read these figures.