Back to projects

Principale Street infrastructure – preliminary design

Tracadie-Sheila, New Brunswick

completeWastewaterCWWF
Federal contribution
$88,642
Federal share50%

of $177.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 7, 2016(actual)
Construction end
Jul 16, 2018(actual)

Against the original forecast

  • Construction end7 weeks lateforecast May 30, 2018

Also in Tracadie-Sheila