Second Water Reserve Tank
Federal contribution
$1.5M
$1,500,000
Federal share75%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Inuvik
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Mar 13, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 1, 2018
- Construction end3 weeks earlyforecast Mar 31, 2020
Also in Inuvik
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47615 in the federal list. How to read these figures.