Back to projects

Purchase a specialized transit vehicle to replace a vehicle

Trent Hills, Ontario

completePublic TransitPTIF
Federal contribution
$40,259
Federal share47%

of $85.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedFeb 10, 2017
ApprovedMar 19, 2018
2018
Built

Approved 13 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Municipality of Trent Hills
Construction start
May 11, 2018(actual)
Construction end
May 15, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Dec 19, 2017
  • Construction end2 weeks earlyforecast May 31, 2018

Also in Trent Hills

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47924 in the federal list. How to read these figures.