Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
20182019
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Oakville
Construction start
Sep 11, 2017(actual)
Construction end
Jan 18, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 1, 2017
  • Construction end7 weeks lateforecast Dec 1, 2018