Back to projects

Installation of 28 new Transit pedestrian shelters to support Transit service

Oakville, Ontario

completePublic TransitPTIF
Federal contribution
$74,679
Federal share50%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Oakville
Construction start
Sep 20, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017
  • Construction end2 months lateforecast Sep 30, 2018

Also in Oakville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48077 in the federal list. How to read these figures.