Replacement of 26 Transit pedestrian shelters at end of useful life

Oakville, Ontario

completePublic TransitPTIF
Federal contribution
$96,000
Federal share50%

of $192.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Oakville
Construction start
Sep 25, 2017(actual)
Construction end
Sep 7, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017
  • Construction end3 weeks earlyforecast Sep 30, 2018

Also in Oakville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48078 in the federal list. How to read these figures.