Back to projects

Installation of digital signage at Bus shelters at the Hospital

Oakville, Ontario

completePublic TransitPTIF
Federal contribution
$43,962
Federal share49%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20172018201920202021
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Oakville
Construction start
Aug 1, 2017(actual)
Construction end
Jul 29, 2021(actual)

Against the original forecast

  • Construction start3 months earlyforecast Nov 1, 2017
  • Construction end16 months lateforecast Mar 31, 2020

Also in Oakville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48082 in the federal list. How to read these figures.