Installation of Accessibility Improvements at Bus Service Stops
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
201720182019
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Town of Oakville
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Nov 7, 2019(actual)
Against the original forecast
- Construction end5 weeks lateforecast Sep 30, 2019
Also in Oakville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48083 in the federal list. How to read these figures.