Completing the installation of the new Transit Information and Communication System

Oakville, Ontario

completePublic TransitPTIF
Federal contribution
$140,000
Federal share50%

of $280.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Oakville
Construction start
Jan 1, 2017(actual)
Construction end
May 31, 2017(actual)

Against the original forecast

  • Construction end10 months earlyforecast Mar 31, 2018

Also in Oakville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48086 in the federal list. How to read these figures.