Planning and design for the replacement of the existing water main and appurtenances from connection point at Elk Street to end of water main
Federal contribution
$9,953
Federal share33%
of $30.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Malahide
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Dec 31, 2017(actual)
Against the original forecast
- Construction start7 months lateforecast Jan 1, 2017
- Construction end2 weeks lateforecast Dec 15, 2017
Also in Malahide