Back to projects

Planning and design for the replacement of the existing water main and appurtenances from connection point at Elk Street to end of water main

Malahide, Ontario

completeDrinking WaterCWWF
Federal contribution
$9,953
Federal share33%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Malahide
Construction start
Aug 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 1, 2017
  • Construction end2 weeks lateforecast Dec 15, 2017