Slip-line existing stormwater culverts located along Springerhill Road and Calton Line
Federal contribution
$37,000
Federal share40%
of $91.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 8, 2019
20192020
Built
Approved 10 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Malahide
- Construction start
- Nov 15, 2019(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start2.9 years lateforecast Jan 7, 2017
- Construction end2 months lateforecast Dec 15, 2019
Also in Malahide
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51869 in the federal list. How to read these figures.