Slip-line existing stormwater culverts located along Springerhill Road and Calton Line

Malahide, Ontario

completeWastewaterCWWF
Federal contribution
$37,000
Federal share40%

of $91.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 8, 2019
20192020
Built

Approved 10 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Malahide
Construction start
Nov 15, 2019(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start2.9 years lateforecast Jan 7, 2017
  • Construction end2 months lateforecast Dec 15, 2019

Also in Malahide