Duffin Creek Wastewater Plant Field Testing for Phosphorus Removal

York, Ontario

completeWastewaterCWWF
Federal contribution
$1.5M
$1,508,674
Federal share50%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jan 1, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction end8 months lateforecast Jul 31, 2018

Also in York

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48982 in the federal list. How to read these figures.