German Mills Creek Bank Stabilization and Sanitary Infrastructure Protection Environmental Assessment

York, Ontario

completeWastewaterCWWF
Federal contribution
$225,000
Federal share50%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jan 3, 2017(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction end3 months lateforecast Mar 31, 2019

Also in York

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48987 in the federal list. How to read these figures.