Sanitary Infrastructure Protection and Stream Rehabilitation of East Don River near Richvale Community Centre: Design and Rehabilitation
Federal contribution
$187,500
Federal share50%
of $375.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- May 1, 2017(actual)
- Construction end
- Sep 14, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 1, 2017
- Construction end13 months earlyforecast Sep 30, 2021
Also in York
- Regional Municipality of York - Transit Fleet Electrification$76.0M
- York Durham Sewage System Forcemain Twinning$43.3M
- Yonge North Subway Extension - Planning and Preliminary Engineering$36.3M
- Groundwater Supply System Improvements to Mitigate Impacts of Extreme Weather Events on Lake Based Supplies$18.1M
- Rehabilitation of the York-Durham Sewer on 16th Avenue the City of Markham$12.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48989 in the federal list. How to read these figures.