Sanitary Infrastructure Protection and Stream Rehabilitation of East Don River near Weldrick Road West: Design and Rehabilitation

York, Ontario

completeWastewaterCWWF
Federal contribution
$225,000
Federal share50%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
May 1, 2017(actual)
Construction end
Sep 14, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017
  • Construction end13 months earlyforecast Sep 30, 2021