Back to projects

Sanitary Infrastructure Protection and Channel Stabilization of Pomona Creek in Royal Orchard Park South: Geomorphic Study

York, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
May 1, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2019

Also in York