Longlac Ward Albany Place Watermain and Sewer Replacement

Greenstone, Ontario

completeDrinking WaterCWWF
Federal contribution
$31,859
Federal share13%

of $240.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Greenstone
Construction start
Jul 4, 2017(actual)
Construction end
Jul 28, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end5 weeks earlyforecast Aug 31, 2017

Also in Greenstone

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49031 in the federal list. How to read these figures.