Longlac Ward Albany Place Watermain and Sewer Replacement
Federal contribution
$31,859
Federal share13%
of $240.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Greenstone
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Jul 28, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end5 weeks earlyforecast Aug 31, 2017
Also in Greenstone
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49031 in the federal list. How to read these figures.